Sunniva Encon LLP · Application NoteAN-099 · Rev 0 · 23 Oct 2026
Energy, utilities and waste heat

Industrial park heat network up to 120 °C

How an industrial park can run a pressurised hot-water network at up to 110–120 °C from heat pumps using a 55 °C waste heat stream, and what it saves against furnace-oil boilers in each factory.

Application#99 District heating, including high-temperature supply up to 120 °C
Temperature band70–120 °C
Sunniva selection5 × SE-WWUHT-27
Replacesfurnace-oil fired boilers in each factory

▶Video: Waste-heat recovery heat pumps

V10 · 2–2.5 min
Waste-heat recovery heat pumps

Lifting warm water from condensers, effluent and process cooling to useful heat

Video coming soon

01Problem statement

  • Many small boilers. Each factory runs its own small boiler with its own fuel store, operator and emissions, often at low part-load efficiency.
  • Waste heat next door. The anchor factory dumps 55–60 °C water to cooling towers while neighbours burn fuel for heat at 80–110 °C.
  • Steam distribution losses. Steam networks lose heat through traps, flash and condensate that is never returned.
  • Losses between fuel and process. Burning furnace oil in a boiler or heater and distributing the heat loses a quarter or more of the fuel's energy before it reaches the process.
  • Compliance, safety and handling. Fired equipment brings boiler inspections, fuel storage and unloading, flue emissions and an attendant on every shift.

02Use case

The reference network serves a small industrial park with a dye house, a food plant and a staff campus. An anchor factory rejects 55–60 °C water from gas-engine jackets and process coolers, and the park lays an insulated pressurised loop with a 110 °C supply and 70 °C return.

Heat userProcess temp.BasisHeat, kWh/day
Dye house substationNetwork 110 → 70 °C2 m³/h × 12 h, 70 → 110 °C1,115
Food plant substationNetwork 110 → 70 °C1.5 m³/h × 10 h, 70 → 110 °C697
Staff campus hot water and heatingNetwork 100 → 70 °C1 m³/h × 8 h, 70 → 100 °C, 10% pipe losses307
Storage and pipework standing losses–about 5%106
Total useful heat2,224

Averaged over 20 running hours, the heat pumps need about 111 kW.

03P&ID

L-101 · Hot primary · 120 °CTT103L-102 · Return · ~90 °CY-STRP-101AP-101Bduty / standbyEXP-101FS101HP-101…105SE-WWUHT-27 · 27 kWP-100SRC-100engine jacket andprocess cooling waterheat source ~55 °CWater-sourceTK-1014,500 L120 °CinsulatedventTT101TT102LT101softenermake-up waterVFDP-102A/BL-201 · Supply header · 118 °CTCV-201TIC201PHE-201Dye house substation105 °Cnetwork 110 °Creturn 70 °CTCV-202TIC202PHE-202Food plant substation100 °CTCV-203TIC203PHE-203Campus substation65 °CL-202 · Return header · ~90 °CNCB-001 existing FO boilerstandby / top-up onlyhot supplyreturnsignalsource waterpumpvalvenormally closedINDICATIVE P&ID · NOT FOR CONSTRUCTIONAN-099 · Rev 0 · Sunniva Encon LLP

Tags: HP heat pump, TK tank, SG steam generator, P pump, PHE plate heat exchanger, TCV temperature control valve, TIC temperature indicating controller (panel), TT temperature transmitter, MT moisture transmitter, PT pressure transmitter, LT level transmitter, FS flow switch, NC normally closed. Process fluids are heated through their own exchanger, coil or jacket.

04Solution

System description

  • 5 × SE-WWUHT-27 (135 kW total) (SE-WWUHT water-source, R245fa) delivering 120 °C, covering the day's 2,224 kWh in about 16.5 running hours.
  • A 4,500 L insulated storage tank decouples the heat pumps from the process peaks.
  • Heat source: engine jacket and process cooling water at about 55 °C. Cooling the anchor factory's 55–60 °C water reduces its cooling tower load.
  • The furnace-oil fired boilers in each factory stays connected behind a normally closed valve as standby.
  • Waste water from the anchor factory at 55–60 °C feeds the heat pump evaporators in a central energy centre and returns to its cooling circuit at about 45 °C.
  • The heat pumps lift the network water from 70 °C return to 110–120 °C into a pressurised buffer tank.
  • Each customer takes heat through its own substation PHE with a heat meter, so network water never enters a process.
  • Existing boilers stay connected at each site as standby until the network has proven itself.

Selected equipment

ModelSE-WWUHT-27 × 5
Heating capacity27 kW each, 135 kW total
COP2.93 at the data sheet's rated condition (60/55 °C source water)
Power inputabout 46.0 kW total at rated conditions
Ratingwater or steam to 120 °C, R245fa
Supply temperature120 °C
Storage4,500 L insulated tank

Ratings from the Sunniva TDS 2026 data sheets.

Control philosophy

TT-101 at the top of the buffer tank stages the heat pumps to hold 110 °C and allows up to 120 °C when demand is high. A differential pressure controller on the network sets pump speed. TIC-201 to TIC-203 at each substation control the secondary side, and the network return temperature is monitored to keep it near 70 °C.

05Energy saving and ROI

Change any input to match a customer's site. Defaults are typical Indian prices for October 2026. The installed cost is a placeholder; replace it with the actual quotation.

Plant
Existing heating
Heat pump
Annual saving–energy + O&M
Simple payback––
Purchased energy––
10-year net gain–after paying for the system
ExistingHeat pump
Daily consumption––
Annual energy cost––
CO₂ per year––
Cumulative cash position, years 0–10

06Benefits

One energy centre

A single plant room replaces several small boilers, with one maintenance team and one set of records.

Waste heat finds a buyer

The anchor factory earns from heat it now rejects, and its cooling towers run lighter.

Billing by heat meter

Each customer pays for measured kWh, which makes costs transparent.

Lower energy cost

Each kWh of electricity delivers about 2.9 kWh of heat at the required temperature, against well under one kWh of useful heat per kWh of fuel burnt.

No flame on site

No burner, flue or fuel tank for this duty, and no fuel deliveries to schedule.

Built-in redundancy

Several machines share the load. If one is serviced, the others and the storage carry most of the day, with the existing heater in reserve.

07Engineering pointers

Site data to collect

  • Waste heat stream flow, temperature and hours
  • Each customer's heat demand, temperature and hours
  • Network route and length
  • Existing boiler fuel use at each site
  • Space for the energy centre
  • Present fuel or electricity use and monthly bill
  • Sanctioned electrical load and spare capacity
  • Space for the heat pumps and storage, with service access

Design notes

  • Pressurisation. Water at 120 °C must be kept at about 3 bar or more to prevent flashing. Use a pressurisation unit and rate all pipework and PHEs accordingly.
  • Low return temperature. Network efficiency depends on a cold return. Specify substations for a 70 °C or lower return and penalise high returns in the heat contract.
  • Buried pipe losses. Use pre-insulated pipe and keep the network compact. Losses above 10% of heat sold usually mean the network is too long for the load.
  • Electrical. About 46 kW of heat pump input at rated conditions, plus pumps and fans. Check spare sanctioned load before ordering.
  • Source stream. The source must give up roughly two-thirds of the heat delivered. Confirm its flow and temperature over a full production day, and filter it before the evaporator.
  • Water quality. Scale forms quickly above 60 °C. Use softened make-up and keep the heat pump loop closed, with process fluids on the far side of an exchanger or coil.

Service and warranty